Continuity tests are used to make sure that the SS7 ISUP interface circuit groups (CIC) are aligned with the physical links (E1/T1) properly.
{{DISPLAYTITLE:Continuity Testing Call Flow (CCR/COT)}}
Toolpack version 2.7 allows users of the TMG to do ISUP Continuity Testing via 3 methods by CIC Group or individual CIC:


== Incoming Continuity testing outside a call ==
{| class="wikitable"
This circuit testing occurs when one of the nodes wants to validate a currently idle circuit.  
|-
It is recommended that the switch first blocks the circuit to prevent calls to use the circuit during the testing.
|rowspan="2"|This article applies to:
|'''Product'''
|'''Version'''
|-
|Tmedia
|2.7
|}


<nowiki>
Continuity tests are used to test the speech or transmission path of SS7 circuits. It also ensures that the SS7 ISUP interface circuits (CIC) are aligned with the same physical links (E1/T1) on both ends.
Toolpack version 2.7 allows users of the TMG to do ISUP Continuity Testing via 3 methods by CIC Group or individual CIC:


Peer SP                                        TMG
== Incoming Continuity Testing Outside a Call ==
This circuit testing occurs when one of the nodes wants to validate a currently idle circuit. It is recommended that the switch first blocks the circuit to prevent calls from using the circuit during the testing.


IAM           - - - - - - - - - - ->  
For ITU:
<pre>
        Peer SP                    TMG
           |                          |
          |---------- CCR ---------->|       
          |                          | (timeslot loopback)
          |---------- Tone ----------\
          |<-------------------------/
          |                          |
          |---------- REL ---------->|
          |<--------- RLC -----------|
</pre>


Check tone    - - - - - - - - - - -|
For ANSI:
<pre>
        Peer SP                    TMG
          |                          |
          |---------- CCR ---------->|
          |                          | (timeslot loopback)
          |<--------- LPA -----------|
          |                          |
          |---------- Tone ----------\
          |<-------------------------/
          |                          |
          |---------- REL ---------->|
          |<--------- RLC -----------|
</pre>


                - - - - - - - - - -
== Incoming Continuity Testing Within A Call ==
This circuit testing occurs when the forward side (originating side) sets the ‘continuity test required’ field of the ‘nature of connection indicators’ IE into the IAM message.


REL            - - - - - - - - - - ->
Successful continuity check:
<pre>
        Peer SP                    TMG
          |                          |
          |---------- IAM ---------->| 'continuity test required'
          |                          |
          |                          | (timeslot loopback)
          |---------- Tone ----------\
          |<-------------------------/
          |                          |
          |---------- COT ---------->| continuity check successful
          .                          .
          .                          .
          .                          .
          |---------- REL ---------->|
           |<--------- RLC -----------|
</pre>


              < -- - - - - - - - - -         RLC
Failed continuity check with retry from Peer SP:
<pre>
        Peer SP                    TMG
          |                          |
          |---------- IAM ---------->| 'continuity test required'
          |                          |
          |                          | (timeslot loopback)
          |---------- Tone ----------\
          |<-------------------------/
          |                          |
          |---------- COT ---------->| continuity check failed
          |                          |
    Retry |---------- CCR ---------->|       
          |                          | (timeslot loopback)
          |---------- Tone ----------\
          |<-------------------------/
          |                          |
          |---------- COT ---------->| continuity check successful
          .                          .
          .                          .
          .                          .
          |---------- REL ---------->|
          |<--------- RLC -----------|
</pre>


== Outgoing Continuity Testing ==
Users of the Tmedia unit can easily generate, out of call, SS7 ISUP Continuity Tests using the web portal.


<pre>
        Peer SP                    TMG
          |                          |
          |<--------- CCR ---------- |       
(timeslot  |                          |
loopback) |                          |
          /---------- Tone ----------|
          \------------------------->| ccr success or fail
          |                          |
          |<--------- REL -----------|
          |---------- RLC ---------->|
</pre>   


For ANSI protocol:
== Configuration ==
Peer SP                                        TMG
*[[Outgoing COT testing|Web Portal v2.7: Outgoing Continuity Testing]]
CCR            - - - - - - - - - - ->
              < -- - - - - - - - - -          LPA
Check tone    - - - - - - - - - - -|
                - - - - - - - - - -
REL            - - - - - - - - - - ->
              < -- - - - - - - - - -          RLC
 
</nowiki> 
 
== Incoming Continuity testing within a call ==
This circuit testing occurs when the forward side (originating side) sets the ‘continuity test required’ field of the ‘nature of connection indicators’ IE into the IAM message.


Peer SP                                        TMG
== External Sources  ==
IAM          - - - - - - - - - - ->
*[ftp://109.167.129.114/doc/ITU-T/Q/Q0784e.pdf Q.784-Isup Basic Call Test Specification]
Check tone    - - - - - - - - - - -|
              - - - - - - - - - - -
COT (successful) - - - - - - - - -->
            <- - - - - - - - - - -            ACM
              - - - - - - - - - - -            Ringing tone
            <- - - - - - - - - - -            ANM
Connectivity - -  - -  - -  - -  - -          Connectivity
REL          - - - - - - - - - - ->
            <- - - - - - - - - - - RLC
 
== Outgoing COT testing ==
 
Peer SP                                        TMG
            < - - - - - - - - - - -            CCR
            |- - - - - - - - - - -            Check tone
              - - - - - - - - - -
            < - - - - - - - - - - -            REL
RLC          -- - - - - - - - - - ->   
   
== Configuration ==
*[[Outgoing COT testing|Web Portal v2.7: Outgoing COT testing]]

Latest revision as of 10:26, 12 September 2022


This article applies to: Product Version
Tmedia 2.7

Continuity tests are used to test the speech or transmission path of SS7 circuits. It also ensures that the SS7 ISUP interface circuits (CIC) are aligned with the same physical links (E1/T1) on both ends. Toolpack version 2.7 allows users of the TMG to do ISUP Continuity Testing via 3 methods by CIC Group or individual CIC:

Incoming Continuity Testing Outside a Call

This circuit testing occurs when one of the nodes wants to validate a currently idle circuit. It is recommended that the switch first blocks the circuit to prevent calls from using the circuit during the testing.

For ITU:

         Peer SP                     TMG
           |                          |
           |---------- CCR ---------->|        
           |                          | (timeslot loopback)
           |---------- Tone ----------\
           |<-------------------------/
           |                          |
           |---------- REL ---------->|
           |<--------- RLC -----------|

For ANSI:

         Peer SP                     TMG
           |                          |
           |---------- CCR ---------->|
           |                          | (timeslot loopback)
           |<--------- LPA -----------|
           |                          | 
           |---------- Tone ----------\
           |<-------------------------/
           |                          |
           |---------- REL ---------->|
           |<--------- RLC -----------|

Incoming Continuity Testing Within A Call

This circuit testing occurs when the forward side (originating side) sets the ‘continuity test required’ field of the ‘nature of connection indicators’ IE into the IAM message.

Successful continuity check:

         Peer SP                     TMG
           |                          |
           |---------- IAM ---------->| 'continuity test required'
           |                          |
           |                          | (timeslot loopback)
           |---------- Tone ----------\
           |<-------------------------/
           |                          |
           |---------- COT ---------->| continuity check successful
           .                          .
           .                          . 
           .                          .
           |---------- REL ---------->|
           |<--------- RLC -----------|

Failed continuity check with retry from Peer SP:

         Peer SP                     TMG
           |                          |
           |---------- IAM ---------->| 'continuity test required'
           |                          |
           |                          | (timeslot loopback)
           |---------- Tone ----------\
           |<-------------------------/
           |                          |
           |---------- COT ---------->| continuity check failed
           |                          |
     Retry |---------- CCR ---------->|        
           |                          | (timeslot loopback)
           |---------- Tone ----------\
           |<-------------------------/
           |                          |
           |---------- COT ---------->| continuity check successful
           .                          .
           .                          .
           .                          .
           |---------- REL ---------->|
           |<--------- RLC -----------|

Outgoing Continuity Testing

Users of the Tmedia unit can easily generate, out of call, SS7 ISUP Continuity Tests using the web portal.

         Peer SP                     TMG
           |                          |
           |<--------- CCR ---------- |        
(timeslot  |                          |
 loopback) |                          |
           /---------- Tone ----------|
           \------------------------->| ccr success or fail
           |                          |
           |<--------- REL -----------|
           |---------- RLC ---------->|

Configuration